Sewer voids

Filling a culvert under the A6

To achieve a complete fill of this culvert we filled the culvert 2 trucks at once, twice in one day.

What's the job?

These two culverts under the A6 near Lelystad (The Netherlands) needed to be filled. The total length of each culvert is 90m1. resulting in more than 200m3 per side.

We needed to achieve complete filling of the pipes. With that, also insure that the most important parts under the road would be filled with our RG22 hardfoam completely.

To achieve a complete fill, we made a plan of action to foam each culvert with two trucks at once. Pipes were inserted in to the half way mark. A second set was inserted 2/3rd of the way and the third set of pipes at 1/3rd. Allowing us to start from the middle and work our way back to insure that the culvert is completely filled.

2x 90m Length of pipe
100x200mm (double check size)
>400m3 Foam used

Filling the culvert

In conclusion, each truck needed to fill approximately 130-150m3 per culvert. Allowing us to fill one of them in the morning, and the second in the afternoon with a second foam team on the job.

 

By doing this, the client has as little burden as possible from our activities. To get a birds eye view of the job and how little disturbance our activities give to the other works to be done, check out our video on the left!

Get in touch

One of our specialists will reply within 1-2 business days.
Not a bot or ai-chat, a real person who can tell you more about what you want to know!

 

Hardfoam Team

Technical Specialists

+31 (0)487 593 778 info@benefil.nl